Project Budget Transferred not visible in report CJI8 (CJ34)

$
0
0

Issue:  Transferred budget not visible in report CJI8.

 

 

Root causeReceiver year not entered in CJ34 when
performing budget transfer between WBS Elements.

 

 

Incorrect entry:

Incorrect 1.png

   
  Entry without receiver year.

 

Incorrect 2a.png


Budget entry flow for posted incorrect document number 100001706

The incorrect posting created inaccurate yearly budget data in report CJI8 for the project.

Incorrect 3.png

 

 

 

  

Incorrect 6.png

To view the entire transfer in CJI8, the report must be executed for Overall values without the year.

Incorrect 5.png

 

 

Incorrect 6.png

How To Correct an incorrect budget transfer entry:

 

 

To correct the entry, a new entry must be created using a negative dollar value in budget transfer transaction CJ34.  See example below.



Incorrect 7.png

Note the negative value in the Amount column.

 

 

Incorrect 8a.png

 

Budget entry flow for posted document number 100001707

 

 

 

Validate reversal in CJI8

 

 

 

Incorrect 9.png

 

 

 

 

 

 

 

 

Incorrect 10.png

 

NOTE:  

 

 

Once the above

 

steps have been performed the budget transfer must be performed again
correctly.  Be sure to enter year for

 

Sender and Receiver WBS Element.

 

 

 

 

 

 

 

 

 

 

 

 