MRP run sales order is not considering MD41

$
0
0

Hi  All,

               

I was trying to run MRP with strategy 10 –MRP against sales orders but system doesn’t consider sales order for MRP run .System consider independent requirement for (MD61) for MRP run.

I run the MRP with MD41- can you please help me to solve it? Should I use any other strategy than 10 for running MRP with sales orders?

 

Thanks for the advise.

 

Regards,

  Vijesh