Re: PP-PM Capacity Planning View in CM25

$
0
0

Hi Karim

When work centers are shared as resources between PP, PM, and PS, there will not normally be any prioritization of the capacity requirements.

The Work Center = Equipment link is used if the work center is a machine. It makes visible if the work center is under maintenance by the help of system condition (work orders).

You may want to take a look at this document:

 

Integration between PP module and PM module

 

 

 

Regards

Savas