Hi,
I am also getting same error. In my scenario SNP optimizer is creating SNP: Plnd Order. This implies availability of resource capacity.
Next we are running PPDS heuristic (infinite scheduling) for conversion of these orders to PPDS: PlOrd within PPDS horizon. PPDS is deleting SNP planned orders but it is not creating new PPDS orders. And it is throwing error. Both these steps were executed through process chain for 1700 products/ across all resources, in one location.
For simulation of this issue: we had executed interactive SNP optimizer for the selective location- product. It is creating SNP planned orders, with date & quantity same as earlier SNP optimizer run. In next step we are executing PPDS run for same location - product, and SNP orders are getting converted to PPDS PlOrd. This implies that there is no error in PPM/ Recipe/ validity date of PPM/ Adequate availability off resource capacity.
What could be the possible reason?
Thanks in advance.
With Regards
Animesh