Re: SAP CM25 with dispatching production orders to individual work center capacities

$
0
0

Thank you Brahmankar.

 

I setup the Split check on Routing & checked the Workcenter to be used by several operations. Looks like it gave me what I needed however I am kind of confused how it is calculating to put several orders in parallel.

 

For example:

 

Shift timing: 7 am to 11 am - 4 hours

No break time

100% utilization

# of individual capacity: 4 ( so total available hours = 16 hours in that shift )

In my order my operation total time is 30 mins setup + 30 mins machine run time = 1 hour

 

so in CM25 how many orders can I run between 7 and 11 am ?

also Split / Allocate function is not highlighted on my CM25, do you know what I am missing ?

 

Thank you