Thank you Brahmankar.
I setup the Split check on Routing & checked the Workcenter to be used by several operations. Looks like it gave me what I needed however I am kind of confused how it is calculating to put several orders in parallel.
For example:
Shift timing: 7 am to 11 am - 4 hours
No break time
100% utilization
# of individual capacity: 4 ( so total available hours = 16 hours in that shift )
In my order my operation total time is 30 mins setup + 30 mins machine run time = 1 hour
so in CM25 how many orders can I run between 7 and 11 am ?
also Split / Allocate function is not highlighted on my CM25, do you know what I am missing ?
Thank you