Re: MRP Planning Run & Forward Scheduling

$
0
0

Hello,

 

In the planning run, the basic dates of the planned orders are determined via the in-house production time from the material master. The order finish date which is determined by the planning run displays the requirements date of the material.

The in-house production time in the material master should be maintained so that no adjustment of the order finish date is required.

This is the case if a scheduling type with forward scheduling has been set in the scheduling parameters (Transaction OPU5) or scheduling has been changed to a today scheduling in order to avoid production dates in the past.

You should generally use scheduling types with backward scheduling for planned orders.

Please refer 46237 - Consulting: determination of the order dates

 

Best Regards,

R.Brahmankar