Re: Excess schedule is getting generated in Mrp.

$
0
0

Hello

 

With a coverage profile, basically, system checks for every MRP element whether the
available quantity is below the minimum stock level. If stock falls below the minimum stock level due to a requirement, the system creates a procurement proposal and thus calculates the procurement quantity, so that the available quantity is replenished up to the target stock level.

 

In your case, the minimum lot size is also considered.

 

The following notes will provide a more detailed explanation of the
range of coverage calculation on MRP:

217144  - Range of covrage calc. w/ range of coverage profile
217080  - Documentation: range of coverage in MRP

 

BR

 

Caetano