Schedule maintenance plan : 1 order

$
0
0

Hello Experts,

 

Please I need your help, I have 4 operations in Task list :

 

Operation 1 : 1 Week

Operation 2 : 2 Weeks

Operation 3 : 1 Month

Operation 4 : 2 Months

 

After 1 month I need 1 order for operation1, 2 and 3 ( 1S, 2S, 1M)

And after 2 months I need also 1 order for all operations ( 1S 2S 1M 2M )

 

This is the result that I have now

 

re.PNG

 

How can I do that ?

 

@ I do not want to change the unit for months

 

Regards,