Hi,
You would like to calculate the quota bucket as 3 hours based upon completion of 12hours work done.
Then you need to modify the 2nd PCR like below
ZUPT
*
****
HRS=M1000
HRS?12
*
LEAVE
=
HRS=3
ADDDB1200Z
HRS=D1000
HRS-D1000
ADDDB1000Z
HRS=M1000
HRS-M1000
ADDMB1000Z
Check and let me know.
Regards,
Sankarsan