Hi Gurus,

 

we have a problem about periodic process order settlement.

 

Status GLFT is set as soon as the correct quantity has been delivered. Then the order is settled and WIP is cleared away. Our problem is that at this time when quantity is delivered there are still some postings of consumption missing. We don't want the order to be settled before Status TABG.

 

Is there any possibility? We thought about changing the Status GLFT in Transaction BS22 to "Settlement not allowed"... But of course we need the WIP calculation in this case. I can not change the Settings in Transaction OKGC...

 

I am thankful for every helpful hint.

 

Thanks!

Sandra